Redcliffe, Queensland
Area: 15,000m2
Hanceys Turf was contracted to Rebuild 2 Baseball fields through MBRC at Talobilla Park, Redcliffe.
The works covered below show what was involved in the project:
Site Setup
Initial Site setup works we engaged the following prior to any machinery onsite.
Prepare 15,000m2 on both fields
Next step in the process was the Surface Preparation and Cultivation:
Turf Installation — 15,000m2 on both fields
Once the site was prepared, we would then be ready for the turf installation. The turf was purposely grown and inspected at our turf farm at Woodford. We would harvest and install the turf on the same day to allow for minimal stress on the turf.
Maintenance — 8 weeks
After the turfing had been done the maintenance period works would start.
Prepared area ready laser graded at 1% ready for turf installation
Irrigation on immediately that turf is installed in sections.
Please note Irrigation was done by Project Irrigation which was part of another project all together and not under us.
First batch of turf starting to be harvested for Talobilla Baseball Fields
Turf Harvesting
Final Day of Turf install on Main field