Bray Park, Queensland
Area: 25,000m2
Total field rebuild to include reshape, surveying new playing surface, irrigation, drainage, establishment and maintenance all within a 8 week window of the Summer school holiday.
PRELIMINARY WORKS
Prior to starting turning dirt onsite we had to engage and comply with all Safety Documentation, Safety signage, Survey of current fields/surrounding land and engage Temporary fencing to the perimeter.
After surveying the field and calculating the soil available and imported turf sand the above design was engaged. As over 7,000 m3 of soil had to be moved, 2 dozers with machine control had been engaged to rough in the surface to +/-25mm with final trimming done with a tractor and laser box blade.
Soil being pushed around
Genesis College selected Hanceys Turf Premium Wintergreen couch wall to wall for all the area to cover the cricket field, soccer fields and athletics areas
At time of field handover the turf was ready for play and the kids to return to school.
12 months on and the field is being enjoyed by the kids