We had been asked by MBRC Moreton Bay Regional Council to engage in the rebuilding of Wendy Allison Soccer field precinct which contains 1 senior full size field and 4 junior fields
The process included:
WHS documentation including Work Method Statement, Site Specific Safety Plan, Construction Schedule
Service location was required before commencing any works, DIAL BEFORE YOU DIG, plans
Site establishment and construction fencing to surround site
Soil tests had been provided by MBRC and soil amendments applied as per the recommendations
Installation of temporary irrigation system is to be installed prior to turf laying
Supply and apply soil conditioner, RRA Organics
Blecavate surfaces
Laser Level Field including Brush and Final Trim
Supply and Install Hanceys Turf Premium Wintergreen turf
Supply and apply Ronstar and starter fertiliser
Supply and apply pesticide as required
Supply and apply controlled release fertiliser
Maintenance:
1st mow and Sweep
2nd Mow, Sweep and Topdressing 10mm
3rd Mow and Sweep
4th Mow, Sweep
5th Mow Sweep and Topdressing 10mm
Maintenance of field for 13 weeks included temporary fence line, mowing and whippering
Line marking ready for play
All machinery used during the works was to be of low compaction
During turf maintenance period the Contractor was to guarantee 100% coverage and establishment of turf through this period
We had to provide warrantees and certificates for turf and materials used in this project
“As Constructed Drawings”
AS THIS SITE WAS SENSITIVE TO ENVIRONMENTAL AND SAFETY REGULATIONS BELOW IS AN OUTLINE WE IMPLEMENT THE FOLLOWING SAFETY PROCESSES AND ACTIONS:
Site log sheet
Site induction
SWMS
JSA
PPE
Safety barrier fencing with dust proof shade cloth
Site safety signs
Machinery inspections
Daily tool box talks
Mandatory flashing lights and reverse beeper on site equipment
Mandatory shields and guards fitted to equipment
Licenced and experienced equipment operators
Safety policy
Environmental policy
Detailed Health and Safety manual with all relevant information easy to refer to and abide by
ENVIRONMENTAL CONSIDERATIONS SITE SPECIFICS:
Specified areas for loading and unloading
Buffer zones
Coir logs or Silt fencing for silt/erosion control
PROGRAM OF WORKS:
Day 1 Site meeting with stakeholders
Day 2 Site setup/safety/GPS pick up/service location etc
Day 3 Herbicide treatments (10 days for die off)
Day 14, 15 Cultivation and shaping
Day 16-20 Earthworks- Import material, cultivation, amendments and shape
Day 21 Final trim and consolidate
Day 22 Pressure test irrigation system
Day 23, 24 Supply, install turf and rolling
Day 24 Fertiliser and pre-emergence
Day 25-90 Grow in mowing and maintenance program
Day 40 Rolling
Day 40 Top dress 1
Day 54 Top Dress 2
Day 55 Commission and hand over after maintenance period
Blecavating of surface after 2 applications of Glyphosate
Site preparation
Irrigation design for Snr and Jnr fields
Final shape of the fields taking into consideration of imported soil, existing volumes and run off areas